Narrative Description of Project
A number of bridges on the Lebanese territory were a target during the Israeli hostilities of July-August 2006. The resulting damages were classified into the following. This project involves six of those bridges along the South Motorway.
Description of Actual Services Provided
The Scope of work has been determined according to the structural and laboratory reports on each of the damaged bridges. A solution was formulated for each and re-construction was supervised accordingly.
The Consultant (TEAM International) has transmitted to the Contractor the as-builts provided by the CDR for each of the bridges below.
The scope of work was determined as follows:
1) Rmeileh / Wardaniyeh PS-4 Demolishing & total reconstruction
2) Rmeileh Village PS-5 Demolishing & total reconstruction
3) Ghazihey Village PS-14 Rehabilitation & jacketing of piers
4) Ghazieh /Kinnareet PS-15 Jacketing of pier & reconstruction of overpass slab
5) Zahrani Interchange Demolishing & total reconstruction
6) Zahrani Multiple-Box-Culvert Demolishing & total reconstruction